The Project
Due to the nature of our scope, our sequencing with the aligned trades was paramount. We put together a document illustrating the 7 stages of install so as not to delay the programme of works. This included leaving a 300mm zone at the base of the rainscreen slab to allow the bricklayer to arrive at the correct course ahead of cavity tray installation.
Scope of Works
SFS
Sheathing Board
Rainscreen Insulation
Brick Tie Channels
Fire Breaks
Cavity Trays
Vents and Cover Plates