0121 707 0077



  • HOME
  • ABOUT US
    • ABOUT US
    • FIS CAMPAIGNS
    • FIT-OUT FUTURES
    • MEET THE FIS BOARD
    • FIS BOARD NOMINATIONS
    • MEET THE SKILLS BOARD
    • MEET THE TEAM
    • MEMBERSHIP VETTING
    • WORKING GROUPS
    • CONTACT US
    • PRIVACY POLICY
  • MEMBER DIRECTORY
  • PROJECT LIBRARY
  • NEWS
  • EVENTS
  • KNOWLEDGE HUB
    • KNOWLEDGE HUB
    • TECHNICAL RESOURCES
    • ORGANISATIONAL CAPABILITY
    • BUILDING SAFETY
    • BUSINESS & LEGAL
    • SUSTAINABILITY
    • HEALTH & SAFETY
    • MENTAL HEALTH
    • DIGITAL CONSTRUCTION
    • ACOUSTIC VERIFICATION SCHEME
    • SUPPORT FOR SPECIFIERS
    • BRITISH STANDARDS
  • MEMBERSHIP HUB
    • MEMBERSHIP HUB
    • BECOME A MEMBER
    • MEMBER BENEFITS
    • MANAGE ACCOUNT
    • AWARDS
    • BRITISH STANDARDS
    • PUBLICATIONS
    • REFER A MEMBER
    • SPONSORSHIP
    • WORKING GROUPS
  • SKILLS HUB
    • SKILLS HUB
    • COMPETENCY TOOLKIT
    • FIS ACADEMY
    • RECRUITMENT
    • CAREERS HUB
    • JOB BOARD
    • QUALIFYING YOUR WORKFORCE
    • FUNDING YOUR TRAINING
    • TRAINING AWARDS
    • FIND TRAINING
      • TRAINING DIRECTORY
      • CPD
  • SPECFINISH
Join us
Sign in

Avon Street, Bristol

Click to watch video

Click to watch video

Click to watch video

1/5

The Project

V&D Interiors delivered the drylining works at Avon Street, Bristol, a major purpose-built student accommodation development comprising 447 bedrooms across three blocks and extending up to 12 storeys.

The scale of the package was substantial, incorporating approximately 219,367 linear metres of metal framing, 86,358m² of plasterboard and 19,620m² of insulation. The works incorporated 13 different wall types, requiring careful coordination across all three blocks to maintain consistent setting out, wall and ceiling lines, levels and junctions.

The highly constrained site presented a significant logistical challenge, with minimal storage and material-handling space, a main road bounding the site and the River Avon to the rear.

V&D implemented a just-in-time delivery strategy to control the significant volume of materials entering the project while maintaining progress. As logistics became increasingly constrained, V&D introduced an additional forklift to support material movements and relieve pressure on the site logistics operation.

Working collaboratively with GMI, British Gypsum and OP Systems, V&D coordinated labour, deliveries, material distribution and multiple construction systems to successfully deliver this substantial package across all three blocks.

Scope of Works

  • Partitions
  • Wall Linings
  • MF Ceilings
  • LIG Ceilings
  • SFS
  • Beam Encasements
  • Plastering
  • Sheathing Board

V&D Interiors

Project Type

  • Drywall Construction - residential

Location

  • Bristol

Value

  • £3.915m

Supplier

  • British Gypsum
  • Dupont
  • Isover
  • OP Systems
  • Promat
  • RCM
  • Rockwool

Architect

  • Chapman Taylor
Arrow Created with Sketch. Back to Gallery